Building Process

Home Building Process
Building Process

From contract signing to final cleaning,

  • Contract signing
  • Building Permit acquired
  • Stake out lot (determine foundation elevation)
  • Excavation of site
  • Footings formed up and poured
  • Foundation formed up and poured
  • Underground plumbing
  • Foundation cures for a week
  • Tar foundation, install window wells
  • Backfill foundation and interior floors
  • Sewer and water lateral connections
  • Permanent power trench
  • Pour basement and garage floors
  • Order windows and doors (Rough opening sizes)
  • Pick out and order appliances (fax to cabinet maker)
  • Finalize cabinet details with cabinet maker
  • Pick out plumbing fixtures and shower valves
  • Decide on roof color and fascia / soffit color
  • Pick out garage door color
  • Pick out and order jacuzzi tub
  • Framing begins
  • Trusses installed, sheet roof
  • Heating and Air conditioning roughed in
  • Order fireplace

 

Order Of Events

J2 Homes builds upon a strong foundation of integrity.

  • Plumbing roughed in
  • Electrical roughed in
  • Built in vacuum, security, sound, intercom, theater systems
  • Pick out floorcoverings (tile, hardwood, carpet)
  • Pick out and order cultured marble
  • Pick out paint color
  • Pick out mantle
  • Finalize and order brick or cultured stone
  • Pick out stucco color
  • Tar paper roof, shingles installed
  • 4-way, shear panel, gas line, permanent power inspections
  • Insulation — inspection
  • Order light fixtures
  • Permanent power and gas meters set
  • Exterior masonry or stucco lathe — inspection
  • Sheetrock — Nailing inspection
  • Secure exterior doors with locking door knobs
  • Pick out countertops
  • Order doors and interior trim moldings
  • Install finish carpentry
  • Interior handrail installation
  • Fireplace mantle installed
  • Install tile floors, hardwood floors

 

Custom Crafted Excellence

Client Decisions In Red.

  • Install cabinets
  • Order countertop templates for granite or solid surface
  • Install cultured marble
  • Painting (includes exterior doors)
  • Order garage door
  • Fascia, soffit and gutter installed
  • Grade for concrete and finish grade yard
  • Pour concrete sidewalks, stairs, patios and driveway
  • Plaster foundation
  • Order permanent water meter from city
  • Finish deck
  • Order exterior handrails
  • Finish electrical
  • Insulate roof
  • Appliance delivery
  • Install countertops
  • Mirrors and shower doors installed
  • Plumbing finish
  • Carpet installation
  • Heating finish and A/C unit installation
  • Hang doors
  • Hardware installation
  • Walk thru, make a list of corrections
  • Change utilities into owners name
  • Schedule closing date, long-term financing
  • Final cleaning